Assessment of cost and schedule performance in construction of key nuclear reactors
Кароль Скіба et al · Kyiv National University of Construction and Architecture · 2025
Acceso al recurso
Entrá al contenido desde la opción principal o elegí otra fuente disponible.
Acceso abierto al texto completo
Resumen
Descripción general del contenido del recurso.
complexity of design, tight on-site schedules, and a logistically sophisticated end-to-end supply chain, to name just a few, make the entire project highly
prone to complications. In 2017, it was estimated that nearly two-thirds of the 55 nuclear plants under construction at that time were behind schedule.
Furthermore, since 2010, delays of this nature have been believed to have contributed to an almost 20% increase in the final costs of the projects. This
work analyzed recent construction performance of Generation III/III+ nuclear reactor projects, specifically examining AP1000, EPR, and
APR1400 technologies. Key performance indicators evaluated included planned versus actual construction times, costs, and capacity construction
rates, revealing significant deviations across the analyzed projects. Each nuclear project's performance was quantitatively assessed using the
schedule performance ratio, cost performance ratio, and an integrated performance coefficient to comprehensively compare efficiencies across
different reactor technologies. Analysis further identified key reasons behind these deviations, such as evolving regulatory environments, safety
requirements, project management inefficiencies, supply chain immaturity, and limited skilled workforce availability, which contributed to
persistent first of a kind (FOAK) challenges and obscured the anticipated nth of a kind (NOAK) improvements. Based on these findings,
recommendations are provided for future research, emphasizing the necessity to apply insights gained from large reactor deployment challenges to the emerging Small Modular Reactor (SMR) technologies.
Cómo citar
Elegí el formato que necesitás y copiá la referencia al portapapeles.
APA 7
al, К. С. E. (2025). Assessment of cost and schedule performance in construction of key nuclear reactors. https://doi.org/10.32347/2522-4182.16.2025.5-21
MLA
al, Кароль Скіба et. "Assessment of cost and schedule performance in construction of key nuclear reactors." 2025. https://doi.org/10.32347/2522-4182.16.2025.5-21.
Chicago
al, Кароль Скіба et. 2025. "Assessment of cost and schedule performance in construction of key nuclear reactors.". https://doi.org/10.32347/2522-4182.16.2025.5-21.
Harvard
al, К. С. E. 2025, Assessment of cost and schedule performance in construction of key nuclear reactors, Kyiv National University of Construction and Architecture, available at: https://doi.org/10.32347/2522-4182.16.2025.5-21 [Accessed 23 Jun. 2026].
Detalles del recurso
Información bibliográfica útil para confirmar que se trata del material correcto.
- Título
- Assessment of cost and schedule performance in construction of key nuclear reactors
- Autor / colaboradores
- Кароль Скіба et al
- Editorial
- Kyiv National University of Construction and Architecture
- Año de publicación
- 2025
- ISSN
- 2522-4182
- ISSN
- 2522-4182
- Idioma
- eng
Materias
Explorá otros recursos relacionados a partir de estas materias.